Wiesbaden – Kaiser Friedrich Ring
Client
City of Wiesbaden
Construction time
August 2021 – October 2021
Reconstruction of accident blackspot Kaiser-Friedrich-Ring, Wiesbaden
Main works
- Construction of traffic islands with lowered crossing kerbs
Overview
- Paving work 200 m²
- Asphalt work 350m³
- Construction of foundations for new LSA system (5 pieces)
- Laying of empty pipes for power supply
Special features
- Work with large machinery in confined spaces
- 10 construction phases