A661 – Bad Homburger Kreuz

Client
Autobahn GmbH des Bundes
Construction time
July – August 2022
Ramp program 2022
Bad Homburger Kreuz
Main works
- Banquet works
- Base course works
- Asphalt works (base course/binder course/cover course)
- Fault clearance works
Overview
- 350 m³ of banquet work
- 11,200 m² Hydraulically bound base courses construction
- 11,100 m² asphalt removal/paving
- 1,750 m construction of joints
Special features
- Construction time in the summer holidays due to the traffic junction