FES Frankfurt

Auftraggeber

Client

FES Frankfurter Entsorgungs- und Service GmbH

Bauzeit

Construction time

March 2019 to May 2019

Production of a base plate for a glass handling station for receiving bulk boxes.

Special features

No reinforcement was laid in the floor slab, steel fibre components were added to the concrete. In addition, heavy Vignol rails were laid on the floor slab and mounted non-positively with the floor slab. This protected the surface of the base plate from mechanical stress.