KVP Kelsterbach

Auftraggeber

Client

Municipal

Auftragsvolumen

Volume

1.179.000 Euro

Bauzeit

Construction time

May 2019 bis February 2020

KVP Kelsterbach

Main works

  • Laying of supply and disposal lines
  • road works

Overview

  • approx. 2500 m³ earthworks
  • approx. 800 m cable conduits
  • approx. 160 m connecting pipe for road drainage
  • approx. 160 m connecting pipe for road drainage
  • approx. 3000 m² asphalt work in 3 layers including semi-rigid wearing course
  • approx. 400 m edging
  • approx. 500 m² paving work
  • 16 lighting poles with approx. 200 m cable trench
  • 9 masts for LSA incl. foundations
  • Tactile surface plates at 4 transitions

Special features

At the intersection of Mörfelder Straße and Südliche Ringstraße, the existing intersection including the LSA is being demolished and used as a roundabout. The expansion will take place in 3 phases with flowing traffic.