KVP Kelsterbach
Client
Municipal
Volume
1.179.000 Euro
Construction time
May 2019 bis February 2020
KVP Kelsterbach
Main works
- Laying of supply and disposal lines
- road works
Overview
- approx. 2500 m³ earthworks
- approx. 800 m cable conduits
- approx. 160 m connecting pipe for road drainage
- approx. 160 m connecting pipe for road drainage
- approx. 3000 m² asphalt work in 3 layers including semi-rigid wearing course
- approx. 400 m edging
- approx. 500 m² paving work
- 16 lighting poles with approx. 200 m cable trench
- 9 masts for LSA incl. foundations
- Tactile surface plates at 4 transitions
Special features
At the intersection of Mörfelder Straße and Südliche Ringstraße, the existing intersection including the LSA is being demolished and used as a roundabout. The expansion will take place in 3 phases with flowing traffic.