Stadtwerke Offenbach

Auftraggeber

Client

GBM Service GmbH Offenbach

Bauzeit

Construction time

June – July 2022

Stadtwerke Offenbach

Main works

  • Civil engineering for cable works
  • Building foundations for transformer
  • Placement of charging stations

Overview

  • 100 m³ earth excavation
  • 10 km laying cables

Special features

  • Parallel execution with 3 subcontractors