Harbour quarter – south construction site

Auftraggeber

Client

Company Thomas Schleser

Bauzeit

Construction time

24.09.2024 – 10.10.2024

Harbour quarter –
south construction site

Main work

  • Asphalt work

Key data

  • Asphalt base course AC 22 TS 50/70, 7 cm thick

  • Colour mastic asphalt Colour 0/8 – grey, 3.5 cm thick – area approx. 120 m²

  • Asphalt grinding with planetary grinder by Bitu-Print

Special features

  • Cramped conditions (entrance area of a tower block)

  • Material transport and execution of the work by hand