B 38 – Georgenhausen
Client
Hessen Mobil Heppenheim
Construction time
19.03.2021 to 23.05.2021 (weekends only)
B 38 Georgenhausen – L 3115, resurfacing of the road surface
Main works
- Asphalt work
- roadbed construction
Overview
- 9 construction sections over 7 weekends
- 32.000 m² asphalt binder and asphalt surface course
- 12.200 to of milled material
- 3.100 to asphalt base course
- 5.800 to asphalt binder
- 3.300 to asphalt wearing course
- 5.400 m of verge work
Special features
The construction periods for this project are particularly short and only take place on weekends.
The procedure is as follows:
- Friday night milling
- Saturday asphalt paving
- Sunday road markings and joints
- Monday at 04:00 a.m. traffic release