B 38 – Georgenhausen

Auftraggeber

Client

Hessen Mobil Heppenheim

Bauzeit

Construction time

19.03.2021 to 23.05.2021 (weekends only)

B 38 Georgenhausen – L 3115, resurfacing of the road surface

Main works

  • Asphalt work
  • roadbed construction

Overview

  • 9 construction sections over 7 weekends
  • 32.000 m² asphalt binder and asphalt surface course
  • 12.200 to of milled material
  • 3.100 to asphalt base course
  • 5.800 to asphalt binder
  • 3.300 to asphalt wearing course
  • 5.400 m of verge work

Special features

The construction periods for this project are particularly short and only take place on weekends.
The procedure is as follows:

  • Friday night milling
  • Saturday asphalt paving
  • Sunday road markings and joints
  • Monday at 04:00 a.m. traffic release