Henninger Turm – Frankfurt a. M.

Auftraggeber

Client

CONCEPTAPLAN Baubetreuungs- und Vertriebsgesellschaft für Haus- und Grundbesitz mbH

Bauzeit

Construction time

March 2015 to July 2019

Development work on the former Henninger Bräu site

Main works

  • Terrain profiling, laying of supply and disposal lines
  • Road works
  • Reconditioning, sieving and breaking of RC material.

Key data

  • approx. 18,000 m³ earthworks
  • approx. 3,200 m cable conduits
  • approx. 540 m drainage pipe diameter, diameter 300-600 mm
  • approx. 300 m road drainage connection pipe
  • approx. 32 road inlets
  • approx. 3,700 m² asphalt work
  • approx. 3,500 m edging
  • approx. 3,400 m² paving work
  • 42 lighting poles with approx. 700 m cable trench