Industrial hall in Meudt
Client
Orben Wasseraufbereitung GmbH & Co. HG
Construction time
05. – 08. November 2019
Industrial hall in Meudt
Main works
- Mastic asphalt screed on a separating layer
Overview
- approx. 1.300 m² mastic asphalt installation
- approx. 260 m² edge storage with Titacord
- approx. 1.300 m² mastic asphalt surface blasted with quartz sand
Special features
- The hall at Industriestr. 6 was built with one layer of mastic asphalt (3.5cm thick) on a separating layer by hand. Approx. 40 tons of mastic asphalt were laid daily.