Kronberg – Westerbachstraße
Client
City administration Kronberg im Taunus
Volume
1.300.000 Euro
Construction time
January 2020 to October 2020
Kronberg, Fundamental renewal of Westerbachstraße
Main works
- Earthworks
- Sewerage
- Water supply
- Road construction
Overview
- Length of the construction project: 560 m
- 330 m PP pipes DN 300 laid
- 3 shafts, 24 gullies
- 380 m drinking water pipeline
- 1200 m street lamp cable with 12 lamp foundations
- 3700 m² AC 32 TN, 10 cm and AC 8 DN 4 cm
- 1100 m² multi-size plaster 10 cm platinum medium
- 1260 m paved channel
- approx. 1500 m different curbs
Special features
Implementation of 5 construction phases