Ciba Vision – Großwallstadt
Client
Company Dreßler Bau GmbH
Construction time
March 2015 (1st construction phase)
March – April 2018 (2nd construction phase)
Parking deck extension (total area 2,200m2) in Großwallstadt
The parking deck was extended in two construction phases, each with 1,100m² per phase.
The extension of the parking deck created 96 additional parking spaces.
An overview of the work carried out:
- Shot peening of the concrete surfaces
- Application of an epoxy resin primer and sealant
- Application of a bitumen welding sheet with a high support inlay
- Sealing of the upstands with a liquid plastic up to 15cm above the water-bearing level
- Paving the mastic asphalt protection and wearing course
- Lay joints and cast with bitumen