Obertiefenbach – Reconstruction bus stop
Client
VLDW – Verkehrsgesellschaft Lahn-Dill-Weil mbH
Construction time
February 2019 to April 2020
Reconstruction of bus stop in Limburg/Weilburg district
Main works
- Paving work
- Canal and drainage work
- Curbstone work with Kassel kerb
- Asphalt works
Overview
- 6.000 m² Paving
- 900 m² Asphalt works
- 690 m³ Earthworks
- 4.000 m Curbside works
Special features
Asphalt work with semi-rigid surface course in Bad Camberg main station (ZOB) and ongoing traffic Half-sided closure with 3-phase traffic lights