Königstein – Falkenstein

Auftraggeber

Client

J. & W. Ferschke GmbH

Bauzeit

Construction time

17.05.2024 – 19.06.2024

Asphalt work
Königstein – Falkenstein

Main work

  • Asphalt work

Key data

  • Asphalt base course AC 32 TS 10 cm thick, approx. 230 m²

  • BAM COLOUR SMA 8 special mix in beige 4 cm thick, approx. 230 m²

  • Installation with paver and by hand

Special features

  • The paving area is an access road with a gradient of up to 19 %, which makes paving and compaction considerably more difficult

Construction site tour

Vimeo

By loading the video you accept the privacy policy of Vimeo.
Learn more

Simultaneously you accept the usage of the Content Delivery Network Cloudflare which is used by Vimeo
Learn more

Load video