Frankfurt – Hanauer Landstraße 211
Client
Company Thomas Schleser
Construction time
14.06.2024 – 03.07.2024
Frankfurt
Hanauer Landstraße 211
Main works
-
Laying of asphalt base course and coloured mastic asphalt surface course
Key data
-
Asphalt base course AC 22 TS – 12 cm thick
-
BAM COLOUR mastic asphalt MA 5 in green – 3.5 cm thick: approx. 125.00 m²
Special features
-
The asphalt base course and the colour mastic asphalt were laid by hand
-
The green mastic asphalt was ground down by Bituprint after paving