Hall 5 Fair – Frankfurt
Client
Messe Frankfurt Venue GmbH
Construction time
March 2018 bis June 2019
Process media line reallocation and site clearance hall 5
Execution of civil engineering works for pipeline laying
New installation of cable conduit routes
Overview:
- approx. 3,500 m³ earthworks
- approx. 7,000 t soil disposal
- approx. 1,600 m² re-paving
- approx. 2,500 m² shoring work
- approx. 2,200 linear metres of cable protection pipes DN 110 / DN 160
Special features:
- Preliminary clearing of the construction site and partial redevelopment of Hall 5
- Work in hall areas under height and swivel limitation
- 2 x 23 t prefabricated shafts as connecting structures to the engineering corridor