PPR-Kreuzung
Bildquelle (Hauptmotiv & Galerie 3-6): Heiko Rhode
Client
City of Bad Homburg & Hessen Mobil
Volume
670.000 Euro
Construction time
July 2018 bis September 2018
PPR crossing
Main works
- Conversion of intersection and ceiling renewal in the area towards the city centre and Dornholzhausen (city of Bad Homburg)
- Basic renovation B456 FR FFM, ceiling renovation B456 FR Usingen (Hessen Mobil)
Overview
- Construction time (scheduled): 24-26 weeks
- Construction time (actual): 8 weeks WS + 2 weeks traffic light company = 10 weeks total construction time
- Construction phases (scheduled): 13
- Construction phases (actual): 5
- approx. 4,300 m² asphalt work
- approx. 920 m² road opening
- approx. 150 m² earthworks
- approx. 1,200 m cable conduit
- approx. 1,500 m² pavement
- approx. 130 m on-board system
- In addition, work for LSA, lighting and drainage
Special features
All the work was carried out while maintaining the flow of traffic, with only very minor obstructions/restrictions for road users.