Hanau – Orangery

Auftraggeber

Client

Hanau Immobilien- und Baumanagement (Owner-operated company of the city of Hanau)

Bauzeit

Construction time

December 2020 to February 2021 with scheduled work breaks

Hanau Schloss Philippsruhe – Change of use of the Orangery

Main works

  • Grading of the existing surface
  • Asphalt paving, base and surface course (both by means of 2D control)
  • Coating of the finished asphalt surface

Overview

  • approx. 700 m² subgrade
  • approx. 175 tonnes AC 32 TS
  • approx. 70 tonnes AC 11DN

Special features

Feeding of the material only possible through small gate opening by feeder.