Gießener Straße – Frankfurt a. M.

Auftraggeber

Client

Office for Road Construction and Development

Auftragsvolumen

Volume

1.350.000 Euro

Bauzeit

Construction time

February 2017 to March 2018

Cycling route Gießener Straße, Frankfurt am Main

Main works

  • Laying of supply & disposal lines
  • road works

Overview

  • approx. 2,500 m³ earthworks
  • approx. 800 m cable conduits
  • approx. 100 m road drainage connection pipe
  • approx. 15 street inlets
  • approx. 11,000 m² asphalt work (& asphalt surface milled off)
  • approx. 800 m edging
  • approx. 3,600 m² paving work
  • 16 lighting poles with approx. 200 m cable trench
  • Light signal systems 7 masts incl. foundations
  • Clock plates at 12 transitions

Special features

Between the Weinstrasse and the Homburger Landstrasse, the already completed footpath on the subway track side had to be taken up again, as the planned lighting masts could not be erected, because a high-pressure gas pipeline was found at the planned location of the lighting poles. In order to erect the new lighting poles, a new power cable had to be laid in the sidewalk. Due to this obstruction, the work was interrupted for 10 weeks and attached to the planned construction time at the back.